REFENCE DETAIL


Following Installations Were Completed Within This Project;

 
33.000m Road Lighting
9 MV Substations
34.000m Overhead Energy Distribution Lines With Steel
And Concrete Poles
95.700m LV Underground Cable
8.600m MV Underground Cable